Welcome

Anti Essays offers essay examples to help students with their essay writing.

Sign Up

Devryproj 592 Quiz 6 - Updated Essay

  • Submitted by: khanarahool
  • on August 6, 2015
  • Category: Miscellaneous
  • Length: 774 words

Open Document

Below is an essay on "Devryproj 592 Quiz 6 - Updated" from Anti Essays, your source for research papers, essays, and term paper examples.

DeVryProj 592 quiz 6 - Updated

IF You Want To Purchase A+ Work Then Click The Link Below   , Instant Download

http://www.hwspeed.com/DeVry-Proj-592-quiz-6-updated-48788333.htm?categoryId=-1
If You Face Any Problem E- Mail Us At   JOHNMATE1122@Gmail.Com
Question 1. Question : (TCO B) Using the network below and the additional information provided, find
(a) the crash cost per day per activity;
(b) which activities should be crashed to meet a project deadline of 12 days at minimum cost; and
(c) what the extra cost is to crash the project.
Activity Normal Time Crash Time Normal Cost Crash Cost
A 5 3 $300 $600
B 3 2 $250 $450
C 6 4 $400 $500
D 5 3 $150 $400


A.
Question 2. Question : (TCO E) The following information is extracted from a project to develop a state-of-the-art alternative power energy storage device.
Activity Duration Predecessors Resources
A           4 days             --             1 research engineer
B           3 days             A             1 test engineer
C           5 days             A             1 design engineer
D           2 days             A             1 marketing specialist
E           3 days             B             1 prototype builder
F           4 days             D             1 test engineer

The owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split.

(a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources are involved, and the quantity required.
(b) Given the owner's stipulation regarding project continuity and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?
Question 3. Question : (TCO F) The following data were obtained from an information systems project to upgrade and expand a local area network....

Show More


Citations

MLA Citation

"Devryproj 592 Quiz 6 - Updated". Anti Essays. 14 Dec. 2018

<http://parimatch-stavka7.com/free-essays/Devryproj-592-Quiz-6-Updated-759221.html>

APA Citation

Devryproj 592 Quiz 6 - Updated. Anti Essays. Retrieved December 14, 2018, from the World Wide Web: http://parimatch-stavka7.com/free-essays/Devryproj-592-Quiz-6-Updated-759221.html


Dispensadores de jabón y loción | Person of Interest | Seenda (3)